Friedrich & ClementBETA

How to bid in this country: portals, deadlines, thresholds →

Completion Plaza Mirador De La Cruz In Canjáyar 15PPOS24-27BI

Finalización Plaza Mirador De La Cruz En Canjáyar 15PPOS24-27BI — original title

ESSpain · AlmeríaBELOW THRESHOLD — NOT ON TED

Your path to submission

  1. Deadline: 9 November at 23:59 — 9 days left.
  2. You submit on PLACSP — Plataforma de Contratación del Sector Público — not here and not by e-mail. ↗ Submission via the Plataforma de Contratación (PLACSP): registration plus a recognised digital certificate / eIDAS signature — as an EU bidder, arrange this early; it typically takes days. Sort out account and signature first — not on submission day.
  3. Collect your evidence — use the eligibility analysis on this page: it lists the requirements and, for known certificates, how to get them.
Compiled automatically from notice and documents — no guarantee; the procedure's wording is binding.

Contract

TypeWorks
Estimated value€169,588
Published19 Oct 2026
ProcedureOpen procedure

Type of service

45 · Construction work
CPV 45233262

Clement What the numbers say about this buyer

  • In this sector the buyer awards roughly every month (527 awards, most recently October 2026) — the next award is due around December 2026 by that rhythm. The last award went to Fircosa Desarrollos S.L.n = 527
  • 46% of this buyer's awards went to companies that had already won here before (1,571 awards since 2018, spread over 560 companies). 54% went to new names.n = 1,571 awards since 2018
  • The median procedure drew 3 bids (466 procedures with a bid count); 28% ended with a single bidder. Sector: median 4 bids.n = 466
  • The award came in at a median 86% of the estimated value (953 awards with both estimate and value) — pricing at the estimate is usually too high here. Sector: 90%.n = 953
  • Across 9 procedures with structured selection criteria, this buyer most often required: Environmental management (6 of 9), References: services (3 of 9), Minimum annual turnover (3 of 9).n = 9

From this buyer's documented awards; comparison values from the same sector and country. Not a forecast, not legal advice. As of 30/10/2026.

Tender documents at a glance

The essentials of the tender documents, checked statement by statement against the documents. For your bid, the original documents count.

Powered by eBriefing – EU language technology. Friedrich is an independent service, not an EU offering.

✓ found in the documents · ❓ not found in the documents or general statement

Tender for construction works: “Finalización Plaza Mirador de la Cruz en Canjáyar” (Almería)

The input text concerns a Spanish public works tender launched by the Diputación Provincial de Almería (local authority in Spain) for the “Finalización Plaza Mirador de la Cruz en Canjáyar”, published on the Plataforma de Contratación del Sector Público (PLACSP).

It describes the legal and administrative setup of the contract, its budget and execution period, the solvency requirements for bidders, and the award criteria.

The point of view and legal references are clearly those of Spain, under Ley 9/2017 de Contratos del Sector Público and related local regulations.

Such as background information, the documents explain that the Junta de Gobierno de la Diputación de Almería approved the project and the contracting file by acuerdo of 25/05/2026, for a works contract (“Tipo de Contrato: Obras, Subtipo: Construcción”) under an “procedimiento abierto simplificado”.

The contract is not subject to EU harmonised regulation and is classified under CPV 45233262 – “Trabajos de construcción de zonas peatonales”.

The estimated value of the contract is 169.587,54 EUR, with a “presupuesto base de licitación” of 205.200,92 EUR (169.587,54 EUR without taxes plus 35.613,38 EUR VAT).

Financing is split between municipalities (Ayuntamientos) and the Diputación, and the expenditure is plurianual over 2026–2027.

Regarding what the bidder must submit and minimum qualification requirements, the tender uses two envelopes: Sobre B for “Documentación administrativa y criterios cuantificables automáticamente” and Sobre A for the “Oferta técnica o evaluable mediante juicio de valor”.

Such as detailed solvency requirements, the text stipulates: (1) Technical-professional solvency: a signed list (“Relación, debidamente firmada”) of main works carried out in the last five years belonging to the same group/subgroup of classification as the contract (or the most relevant group/subgroup if multiple) where the accumulated annual amount in the year of greatest execution is equal or greater than 70% of the “anualidad media” of the contract; (2) Economic-financial solvency: a professional indemnity insurance (“Seguro de indemnización por riesgos profesionales”) with coverage equal to or greater than the “presupuesto base de licitación”, in force at least until the end of the offer submission period, together with a commitment to renew/extend it so that coverage is maintained throughout the entire execution of the contract.

No formal contractor classification is required (“Solvencia requerida: Sin clasificación”).

Submission of offers is electronic through the PLACSP, and bidders must also comply with standard Spanish public procurement documentation requirements as set out in the PCAP and referenced legal articles.

Show all 29 statements

On the scope of the contract—what, how much, where and when—the object is explicitly “Finalización Plaza Mirador de la Cruz en Canjáyar (referencia 15PPOS24-27BI)”.

Such as geographic details, the place of performance is in the province of Almería, territorial code ES611, Spain, in the municipality of Canjáyar.

The execution period is “Plazo de Ejecución: 180 días” from contract start.

Technical quantities and detailed works are contained in the “Proyecto de obra” and “Pliego de Prescripciones Técnicas”, referenced by URL but not reproduced in the excerpt.

Concerning award criteria and weighting, the conditions of adjudication clearly distinguish between criteria evaluated by formula and those evaluated by judgment of value.

Such as quantitative criteria, “Precio” (price) is evaluated by formulas and has a weighting of 75 points.

Such as qualitative criteria, the “Oferta técnica” (technical offer) is evaluated by judgment of value and has a weighting of 25 points.

Subcontracting is allowed (“Subcontratación permitida”), there is no electronic auction (“Se adjudicará mediante subasta electrónica: No”), and the validity period of the offer is three months (“Plazo de Validez de la Oferta: 3 Mes(es)”).

The tender accepts electronic invoicing and payment but not electronic ordering (“pedido electrónico: No; factura electrónica: Sí; pago electrónico: Sí”).

Regarding risks and special conditions, the text highlights financial guarantees and an environmental execution condition but does not detail penalties or site visits in the excerpts.

A special condition of execution of an environmental nature is included: “Consideraciones de tipo medioambiental – REDUCCIÓN HUELLA MEDIOAMBIENTAL”, meaning the contractor must comply with environmental measures aimed at reducing the environmental footprint.

Programs of financing do not include EU funds (“No hay financiación con fondos de la UE”).

Deadlines for questions and any mandatory site visit are not explicitly described in the provided text, although the “Plazo de obtención de pliegos” is given as 09/11/2026 at 23:59, and the tender was published on 19-10-2026.

The tender is processed as “Tramitación ordinaria”.

Such as references to previous procedures, one resolution states that a prior tender was cancelled because the awarded company failed to comply with PCAP requirements (“empresa licitadora al no cumplir los requerimientos del PCAP”) and that a new tender is opened “en los mismos términos y condiciones de la licitación anterior”.

The budget figures (169.587,54 EUR as the estimated value and untaxed amount, 205.200,92 EUR total) and the execution period (180 days) are consistently repeated across the different PDF/text excerpts.

No direct contradiction in conditions (e.g. differing solvency levels, execution periods or criteria weightings) appears; when in doubt, the applicable statements are those in the PCAP and PPT referenced by URL and formally approved by the Junta de Gobierno, which the text explicitly identifies as the governing documents of the contract.

Add your company details — we'll show whether you meet turnover, insurance and reference requirements →

Only the contracting authority's tender documents are binding. As of: 20/10/2026

Clement
References and certificates from your home country count fully across the EU — that is what European procurement law is for.
The Russia sanctions declaration (Art. 5k) comes with nearly every procedure — a formality, but missing it means exclusion.

Eligibility analysis from the tender documents

Tender documents — direct download

⤓
Pliego_CAP.pdf
Legal document
⤓
Pliego_PPT.pdf
Technical specification
⤓
MemoriaJustificativa.pdf
Further document
›
Security deposit: 2 5

Who has won at this buyer so far

Across all contract types of this buyer — not just this sector. A city buys software and fire engines through the same purchasing office.

CompanyAwardsPeriod
Construcciones Nila S.A802020–2026
AGUAEMA SOCIEDAD LIMITADA · ALMERIA432022–2026
FIRCOSA DESARROLLOS, S.L.342021–2026
SPECIALIST COMPUTER CENTRES SL · ALACANT202019–2026
Proyectos y Vías Almería, S.L.202021–2026
From the recorded awards · regular winners know this buyer's requirements — that is your competition.

How often this buyer tenders this kind of work

2
2020
6
2021
119
2023
141
2024
121
2025
227
2026
616 procedures in this category since 2019. Public procurement repeats itself — those who know the rhythm prepare instead of reacting.

Contracting authority contact

·
Deadline — Monday 9 November at 23:59

Tactics

When this buyer has awarded in this sector, usually about 3 bids came in. A normal field for this market. (Based on 73 completed awards — not a statement about this procedure.)

This procedure allows 22 days between publication and deadline — typical in this country is 27 (median of 7,300 procedures). A normal window for this market.

The deadline falls on a Monday — your last full working day is the Friday before. Have evidence and guarantees together by Thursday.

Foreign bidders

In Spain · Construction work, 90 contracts went to foreign companies over the last 3 years (of 100,713 recorded awards) — mostly from Portugal, Italy, France.

Measured from linked award data; foreign winners bidding through a local subsidiary count as domestic — the true share is higher.

How to bid

Guide: how to apply on PLACSP — Plataforma de Contratación del Sector Público (Spanien) → Registration, signature, fees — from the operator's bidder manual.

Read the full notice — Original + documents
Goes directly to this tender on PLACSP — Plataforma de Contratación del Sector Público. The full specification and all annexes are there.
Put together the evidence
Certificates, references and your price — as set out in the notice.
Submit via PLACSP — Plataforma de Contratación del Sector Público before the deadline
Electronic submission — allow time for the portal registration the first time.
To the procurement portal →
We pull data from millions of notices. If the link here does not work, report it — we will find the right one.

Don't miss the next one

Friedrich finds tenders like this for you — every morning at 7:30, each one checked by Claude (Anthropic) for fit, and he learns from your feedback what your company really does.

Register now