Framework agreement for clearing unnavigable watercourses, canals and their adjoins and mowing rugged vegetation of road edges, canals, verges and wadis

Raamovereenkomst voor het ruimen van onbevaarbare waterlopen, grachten en hun aanhorigheden en maaien van ruige begroeiing van wegranden, grachten, bermen en wadi's — original title

BEBelgiumBELOW THRESHOLD — NOT ON TED

Your path to submission

  1. Deadline for requests to participate: 17 November at 11:00 — 16 days left. Two-stage procedure: by this deadline you submit a request to participate (proof of eligibility). Only shortlisted firms are then invited to submit a tender.
  2. You submit on BDA / e-Procurement Belgium — not here and not by e-mail. ↗
  3. Collect your evidence — the eligibility requirements are listed on this page; for many of them the analysis explains how to obtain them.
Compiled automatically from notice and documents — no guarantee; the procedure's wording is binding.

Contract

TypeWorks
Estimated valuenot published — common for below-threshold procedures
Published8 Oct 2026
Procedures_neg_w_call_24_81

Type of service

45 · Construction work
CPV 45112000

Clement What the numbers say about this buyer

  • In this sector the buyer awards roughly every 5 months (5 awards, most recently August 2025) — by that rhythm the next award was due around February 2026. The last award went to MONUMENT - VANDEKERCKHOVE.n = 5
  • The median procedure drew 2 bids (93 procedures with a bid count); 24% ended with a single bidder. Sector: median 4 bids.n = 93
  • 6% of this buyer's awards went to companies that had already won here before (146 awards since 2018, spread over 60 companies). 94% went to new names.n = 146 awards since 2018
  • The award came in at a median 90% of the estimated value (8 awards with both estimate and value) — pricing at the estimate is usually too high here. Sector: 90%.n = 8
  • 12% of awards went to companies from abroad (146 awards with a known winner country). Sector average: 11%.n = 146

From this buyer's documented awards; comparison values from the same sector and country. Not a forecast, not legal advice. As of 01/11/2026.

Tender documents at a glance

The essentials of the tender documents, checked statement by statement against the documents. For your bid, the original documents count.

Powered by eBriefing – EU language technology. Friedrich is an independent service, not an EU offering.

✓ found in the documents · ❓ not found in the documents or general statement

Public procurement for maintenance of watercourses and roadside vegetation in Leuven

The input text concerns a Belgian public procurement procedure launched by Stad Leuven (City of Leuven) in the province of Vlaams-Brabant for a multi‑year framework agreement relating to works on watercourses and roadside/berm vegetation.

It is clearly written from the Belgian legal and administrative point of view, referencing Belgian laws (wet van 17 juni 2016 on public procurement, relevant Koninklijke Besluiten, ARAB, VLAREA, VLAREBO, etc.) and local regulations of the Flemish Region.

“buitenlandse inschrijvers” for foreign tenderers and EU‑level e‑invoicing rules), so the applicable legal framework and contracting authority context are explicitly Belgian.

As background, the documents describe a framework agreement (“raamovereenkomst”) for: (i) ruimen van onbevaarbare waterlopen, grachten en hun aanhorigheden; (ii) maaien van ruige begroeiing van wegranden en bermen; plus related tasks such as prepared works, traffic management, cleaning and maintenance of watercourses, ponds and basins, pruning and removal of woody vegetation, and felling/removal of trees and stumps.

Such as explained under I.1, the place of performance is the entire territory of the City of Leuven, with works spread over various locations, and the contract is awarded via a simplified negotiated procedure with prior publication.

The framework runs for 48 calendar months, with a presumed start date of 01/01/2027 and a maximum total value of 749,000 EUR excl.

VAT; the city reserves the right to terminate if monitoring shows that this ceiling might be exceeded.

Regarding what the bidder must submit and minimum qualification requirements, the input text specifies several elements.

Such as under I.5, the offer must be accompanied by documents on exclusion grounds (declaration that the tenderer is not in an exclusion situation; uittreksel uit het strafregister for Belgian tenderers; self‑cleaning evidence if applicable).

Combinations without legal personality must submit these documents for each member.

Foreign tenderers must be able to provide all proofs themselves.

Economische en financiële draagkracht is evidenced by registration in a trade/professional register.

Show all 47 statements

Technische bekwaamheid requires a list of analogous works over the last three years, backed by certificates of good execution, specifying description, client, contract value and execution period; at least two attestations are required for both (a) cleaning non‑navigable watercourses and their appurtenances, and (b) mowing rough vegetation of verges/ditches/berms, each with a minimum contract value of 125,000 EUR excl. VAT.

Required contractor recognition is categories B1 and G3 (watercourse cleaning), class 4. The offer must be drafted in Dutch, the inventory completed on the provided form, all documents dated and signed (qualified electronic signature via e‑Procurement), with supporting powers of attorney/statutes attached for signatories.

On scope, quantities, place and period, the contract is defined as a “opdracht tegen prijslijst” where unit prices are fixed and quantities are presumed or expressed within ranges; settlement is based on actually ordered and executed quantities.

Such as in II.5 and the annexes, the presumed quantities are listed in a separate “samenvattende opmeting” (Bijlage B) and detail measurement file, but the city stresses these are not indicative of the total offer amount and may be increased, decreased or deleted without compensation.

The works cover: preparatory and traffic regulation, cleaning and maintenance of watercourses/ditches/pools, mowing works, thinning/removal of woody growth, removal of trees/stumps, additional works on a time‑charge basis (regie uren), materials/works reimbursed via a “som ter beschikking van het bestuur” with a 10% margin, and specific sludge removal where the contractor must document quantities via weigh tickets and VLAREA transport documents.

The framework duration is 48 months, with regular evaluations; the contracting authority may terminate with three months’ notice in case of negative evaluation, the contractor with six months’ notice.

On award criteria and weighting, the input text sets out four criteria totaling 100 points.

Such as in I.10: (1) Price – weight 60, evaluated by “regel van drie” formula (lowest price divided by the bid’s price, times weight 60).

(2) Plan of approach and sustainability – weight 15, including which equipment will be used, planned work method, how sludge/berm cuttings will be removed, and sustainability actions in the work process; scored via a ranking formula that distributes max points across bidders.

(3) Communication and reporting to the city – weight 20, also scored via the same ranking‑based formula.

The contract is awarded to the economically most advantageous tender considering all weighted criteria.

Additional qualitative expectations include careful planning of site traffic, avoiding heavy transport in school environments/routes at start and end of school days except during holidays, and adherence to the city’s “Werftransport” charter.

As to risks and special conditions, the documents include extensive provisions.

Such as I.4 and I.11, prices are subject to indexation only after 12 months from contract signature and only if the framework is expressly extended; the price revision formula uses labour cost indices and applies to the revisable portion, with supporting calculations required.

The commitment period for tenderers is 180 days (Art. 58 KB 18.04.2017).

Subcontracting is limited: no more than 25% of the total contract sum may be subcontracted, and subcontractors must hold the same recognitions and certificates; they may not start work until documents are available.

Insurance requirements are stricter than the generic rules: besides standard accident and liability cover, the contractor must carry “burgerlijke aansprakelijkheid uitbating” including environmental damage, immaterial and bodily harm, with minimum capital 2,500,000 EUR per event, waiver of recourse against the contracting authority, and proof of policy plus premium payment within 30 days of award.

No performance bond (“borgtocht”) and no warranty term (“waarborgtermijn”) apply, but the contractor bears all deductibles and non‑covered damages; all safety signalling, waste transport and water usage are included in unit prices.

Penalties and execution risks are detailed.

Such as II.11, a general standard specifications penalty is set at 400 EUR, plus specific penalties: 120 EUR per damaged/disappeared muskrat/rat control device; 30 EUR per missing boundary marker per day until replaced by a surveyor at contractor’s cost; 900 EUR per irreparably damaged or wrongfully felled tree/shrub; 15 EUR per m² of removed talus; 300 EUR per offence for leaving spoil requiring removal on banks or for unprotected spoil; 300 EUR for not following prescribed execution methods.

Delay‑related penalties include supervision costs of 4,500 EUR/month for contractor‑caused delay (II.12) and 300 EUR per non‑executed or incomplete post per watercourse/ditch for failure to meet partial deadlines (II.13).

In urgent cases the contractor must start within 48 hours of service order (II.14).

The authority can modify presumed quantities, add or remove items without compensation (II.15), and may require Sunday/holiday work at double unit prices for own‑labour items.

The contractor must notify if presumed quantities will be exceeded by more than 10%; only the portion above 10% is payable after explicit approval, and delayed payment of that portion cannot trigger interest.

Works can be suspended due to weather without compensation (II.17), with the contractor maintaining signage and detours at his own cost.

On other special conditions, the documents set procedural and legal obligations.

Such as II.7, e‑invoicing via the PEPPOL platform in XML format is mandatory; the city will not be liable for late payments caused by incorrect or untimely e‑invoicing.

Payment terms are 30 days from acceptance and measurement of works, subject to receipt of a compliant invoice and supporting state of works.

GDPR compliance is addressed, and there is a specific clause on avoiding cooperation with companies profiting from economic activities linked to the illegal occupation/blockade of Gaza, West Bank and East Jerusalem; by submitting a bid, the tenderer declares compliance and must seek alternatives if immediate compliance is not feasible at the start of performance.

A further clause limits the bidder’s right to sue the client’s auxiliaries directly, except in cases of intent, fraud or harm to physical/psychological integrity.

The tender must be signed with a qualified electronic signature; a scanned signature is invalid.

I.11 price revision, insurance clauses and contract duration are repeated), but they appear consistent: the framework duration is always 48 months, start date 01/01/2027; maximum value is consistently 749,000 EUR excl.

VAT; no borgtocht or warranty term apply; subcontracting is capped at 25%; and penalties/boetes are uniformly defined in II.11–II.13 and referenced from Art. 45 and 154 of the KB 14.01.2013.

Where the special conditions deviate from the general regulations (e.g. modification of quantities in II.15, enhanced insurance requirements, absence of warranty term, specific penalties), the text clearly qualifies them as afwijkingen or bijkomende bepalingen.

Therefore, in case of any apparent discrepancy between the standard regulations and these special clauses, the specific provisions of this particular bestek (special specifications for OD_SOW‑26.4/866.13) apply as the lex specialis within the Belgian legal framework cited.

Add your company details — we'll show whether you meet turnover, insurance and reference requirements →

Only the contracting authority's tender documents are binding. As of: 26/10/2026

Clement
References and certificates from your home country count fully across the EU — that is what European procurement law is for.
Anything unclear? Bidder questions are your right — ask in writing, the answer goes to everyone.

Who has won at this buyer so far

Across all contract types of this buyer — not just this sector. A city buys software and fire engines through the same purchasing office.

CompanyAwardsPeriod
Truck Trading Limburg32024–2026
Wonen en Werken Tewerkstelling vzw32025
Geosparc22025–2026
MONUMENT - VANDEKERCKHOVE22025
Vanden Broele nv22024
From the recorded awards · regular winners know this buyer's requirements — that is your competition.

How often this buyer tenders this kind of work

2
2022
50
2024
63
2025
30
2026
145 procedures in this category since 2019. Public procurement repeats itself — those who know the rhythm prepare instead of reacting.
·
Deadline — Tuesday 17 November at 11:00
Deadline for requests to participate

Tactics

When contracts were awarded in this country and sector, usually about 4 bids came in. A normal field for this market. (Based on 1,540 completed awards — not a statement about this procedure.)

This procedure allows 40 days between publication and deadline — typical in this country is 34 (median of 3,233 procedures). A normal window for this market.

Foreign bidders

In Belgium · Construction work, 237 contracts went to foreign companies over the last 3 years (of 2,628 recorded awards) — mostly from France, Germany, Netherlands.

Measured from linked award data; foreign winners bidding through a local subsidiary count as domestic — the true share is higher.

How to bid

Read the full notice — Original + documents
Goes directly to this tender on BDA / e-Procurement Belgium. The full specification and all annexes are there.
Put together the evidence
Certificates, references and your price — as set out in the notice.
Submit via BDA / e-Procurement Belgium before the deadline
Electronic submission — allow time for the portal registration the first time.
To the procurement portal →
We pull data from millions of notices. If the link here does not work, report it — we will find the right one.

Don't miss the next one

Friedrich finds tenders like this for you — every morning at 7:30, each one checked by Claude (Anthropic) for fit, and he learns from your feedback what your company really does.

Register now