Resurfacing of Ninove Road, from the intersection formed by Boulevard Louis Mettewie, Boulevard de la Grande Ceinture and Boulevard Prince de Liège, to the regional boundary
Réaménagement de la chaussée de Ninove, depuis le carrefour formé par le Boulevard Louis Mettewie, le Boulevard de la Grande Ceinture et le Boulevard Prince de Liège, jusqu'à la limite régionale
Belgium · Ministerie van het Brussels Hoofdstedelijk Gewest · how to bid here →
Your path to submission
- Deadline: 24 September at 00:00 — 9 days left.
- The submission point is stated in the notice (link on the right).
- Offer and evidence in: FRA, NLD.
- Collect your evidence — the eligibility requirements are listed above; for many of them the analysis explains how to obtain them.
Clement What the numbers say about this buyer
- In this sector the buyer awards roughly every 3 months (25 awards, most recently December 2025) — by that rhythm the next award was due around March 2026. The last award went to Balteau.n = 25
- The award came in at a median 55% of the estimated value (5 awards with both estimate and value) — pricing at the estimate is usually too high here. Sector: 90%.n = 5
- 13% of this buyer's awards went to companies that had already won here before (95 awards since 2024, spread over 80 companies). 87% went to new names.n = 95 awards since 2024
- 25% of awards went to companies from abroad (95 awards with a known winner country). Sector average: 10%.n = 95
- The median procedure drew 3 bids (41 procedures with a bid count); 5% ended with a single bidder. Sector: median 4 bids.n = 41
From this buyer's documented awards; comparison values from the same sector and country. Not a forecast, not legal advice. As of 13/09/2026.
Foreign bidders
In Belgium · Construction work, 224 contracts went to foreign companies over the last 3 years (of 2,548 recorded awards) — mostly from France, Germany, Netherlands.
Typical field: median 3 (from 5 awards).
What the buyer is looking for
The summary in English is being prepared. The official description below is in the original language (DE).
Show original description (DE)
Travaux de démolition et de réaménagement des trottoirs, chaussées, zones de stationnement, pistes cyclables, zones plantées et massifs infiltrants, quais de tram et bus avec l’installation de mobiliers urbains spécifiques, conformément aux plans et coupes annexés au cahier des charges.
Selection criteria — in the procurement documents
The buyer states in the notice that the selection criteria are in the procurement documents (link on the right), not in the EU form. The document analysis below extracts them from there — bid and evidence in FRA, NLD.
Contract
Who has won here before
| Company | Awards | Period |
|---|---|---|
| VIABUILD | 4 | 2024 |
| Spie Belgium | 3 | 2025 |
| TRAFIROAD | 2 | 2024 |
| Production sa | 2 | 2024 |
| ABOG | 2 | 2024 |
How often this buyer tenders this