Reconstruction of the bridge into a culvert in the route of district road No. 1527E in Krężna together with access roads
Przebudowa mostu na przepust w ciągu drogi powiatowej Nr 1527E w m. Krężna wraz z dojazdami
Poland · Piotrków Trybunalski · how to bid here →
Your path to submission
- Deadline: 6 October at 09:00 — 2 days left.
- You submit on eZamówienia — not here and not by e-mail. ↗ Submission via eZamówienia: account required; above the EU threshold a qualified signature, nationally the 'trusted signature' often suffices — check the wording. Sort out account and signature first — not on submission day.
- Collect your evidence — the eligibility requirements are listed above; for many of them the analysis explains how to obtain them.
Clement What the numbers say about this buyer
- 61% of this buyer's awards went to companies that had already won here before (80 awards since 2021, spread over 32 companies). That is well above the sector norm (34%) — newcomers have a harder time here than elsewhere.n = 80 awards since 2021
- Not one of the 80 awards with a known winner country has gone to a foreign company so far. Sector average: 0%.n = 80
From this buyer's documented awards; comparison values from the same sector and country. Not a forecast, not legal advice. As of 30/09/2026.
Foreign bidders
In Poland · Architecture & engineering, 111 contracts went to foreign companies over the last 3 years (of 39,995 recorded awards) — mostly from Germany, France, Switzerland.
Typical field: median 4 (from 4,644 awards).
What the buyer is looking for
1. The subject of the contract is the preparation of complete design and costing documentation (also called design documentation) together with all arrangements and obtaining a decision on the permit for the construction of the culvert together with the demolition of the existing bridge in Krężna, Wola Krzysztoporska, Piotrków County, Łódź Province. 2. As part of the subject of the contract, it is necessary to perform: - obtain d/c maps on a scale of 1 : 500 - develop a construction project (PZT, technical design, executive design), which will include drawings and descriptions of the technology for the construction of the new facility, - develop a demolition project of the existing bridge facility, - develop a project of permanent traffic organization with approval, - develop a bill of quantities of works and an investor's estimate, - obtain agreements and opinions that will form the…
Show full description
… basis for obtaining a decision on the construction and demolition permit, - develop a water and legal operation, - perform geological surveys - solve possible collisions with foreign devices. - make the surface on the object with accesses (total length not more than 1 km) - design horizontal and vertical markings. On the basis of the prepared documentation, the Ordering Party will submit an application for co-financing from the funds of the general subsidy reserve.
Contract
Who has won here before
| Company | Awards | Period |
|---|---|---|
| Zakład Budowlano - Drogowy DUKT Sp. z o. o., Sp. komandytowa | 20 | 2021–2026 |
| DROMOST Sp. Jawna J. Łaska, M. Łaska, M. Łaska | 7 | 2021–2026 |
| Przedsiębiorstwo Robót Drogowych " PEUK" S.A. | 6 | 2021–2023 |
| ORLEN Spółka Akcyjna | 4 | 2021–2025 |
| Partytrans Patryarcha Sławomir | 4 | 2023–2025 |
How to bid